90-Day Delivery Plan
The delivery plan is structured across three 30-day phases, each with defined objectives, gate criteria, and declared dependencies. Phase 1 proceeds on current baseline; Phases 2 and 3 are contingent on confirmed funding.
Last updated: 30 June 2026
Plan summary
Stabilise and Prepare
CI stabilisation, baseline consolidation, GPU readiness planning, governance evidence packaging, and assessor documentation.
GPU Benchmark Cycle
Funded GPU benchmark cycle with comparative reporting against defined baseline criteria and pilot candidate packaging initiated.
Harden and Demonstrate
Production hardening, pilot-readiness packaging, and stakeholder demonstrations with governance evidence.
Phase 1: Days 0–30 — Stabilise and Prepare
In progress
Objectives
- CI stabilisation and baseline consolidation
- GPU readiness planning with controlled runbook updates
- Architecture documentation completion and assessor packaging
- Governance evidence packaging for submission
- Risk register review and active dependency tracking
- Evidence pack publication and review readiness
Gate criteria
- Baseline evidence pack published and reviewer-accessible
- GPU provisioning pathway confirmed or alternative options documented
- Architecture and evaluation documentation reviewed and current
- Risk register updated with current active mitigations
Dependencies
Phase 2: Days 31–60 — GPU Benchmark Cycle
Planned — funding dependent
Objectives
- Funded GPU benchmark cycle execution
- Comparative reporting against declared Phase 1 baseline criteria
- Model checkpoint publication with provenance records
- Evaluation pipeline hardening and repeatability verification
- Pilot candidate packaging initiated
Gate criteria
- Benchmark report published with reproducible methodology and results
- Comparative baseline documented against Phase 1 declared criteria
- Pilot packaging in draft with at least one UK-hosted infrastructure target documented
Dependencies
GPU quota and provisioning are an actively managed dependency. Multiple provider options have been evaluated. This dependency does not block Phase 1 baseline consolidation, CI hardening, documentation, or governance preparation.
Phase 3: Days 61–90 — Harden and Demonstrate
Planned — Phase 2 completion dependent
Objectives
- Production hardening and reliability baseline establishment
- Pilot-readiness packaging complete
- Stakeholder demonstrations with governance evidence presented
- Deployment pathway documentation for UK-hosted contexts
- Model card and audit evidence publication
Gate criteria
- Pilot-ready deployment package documented for at least one UK-hosted target
- Governance evidence pack complete and reviewed
- At least one structured stakeholder demonstration completed with feedback captured
- Model card published with performance characteristics and limitations declared
Discuss delivery timeline
Request a technical briefing to review the delivery plan, current phase status, and dependency tracking in detail.